by Thato Thatedi

The largest hydro-power project in SA

Construction of station ‘on track’

A scene from the excavation and tunelling project
ingula 2.jpg

When the Ingula project is completed, and up and running, this hydro-power station will serve South Africa’s increasing demand for peak energy to meet the demand of a growing industrial sector and a successful rural electrification programme.

The Braamhoek Joint Venture led by GIBB was appointed for the design and construction supervision of the project. The project, which includes the 40m high RCC Braamhoek Dam and 50m high CFRD Bedford Dam (both completed in 2011), two caverns, four surge tanks, four drainage and ventilation shafts and over 14km of tunnels, is set to be the largest hydropower and tunnelling project in Southern Africa.

Located in the Drakensberg mountain range between Harrismith and Ladysmith, the Ingula Pumped Storage Scheme aims to generate a capacity of 1 332MW with an energy storage capacity of 21 000MWh (15.8 generating hours).

According to Colin Logan, Technical Executive of Dams, Hydropower and Underground Works at GIBB, the project is on track with the last stages of excavation currently taking place.

“We reached some important milestones in 2012,” says Logan. “In January, we completed the excavation of the Machine Hall. Concrete encasement of the first Draft Tube was completed in August and the first Spiral Case was installed shortly after. In December 2012, the second Spiral Case was transported to the Erection Bay. This is currently being prepared for installation.”

The first of the four 333MW pump turbine units is expected to be commissioned in the second quarter of 2014, with the remaining units to start commercial operation in 2014 and 2015.

“To date, excavation of the Surge Chambers is 76% complete and the Surge Shaft’s concrete lining commenced in January. With regards to progress on other underground structures, work on the installation of the steel linings for the High Pressure Inclined Shafts is 40% complete. We will use approximately two kilometres of steel lining for the two underground waterways,” says Logan.

In total, there are four pumped storage stations in South Africa, which includes Ingula. “We are proud to be an integral part of the largest hydro-power and tunneling project in South Africa,” says Logan.

comments powered by Disqus

R1

This edition

Issue 39
Current


Archive